Issue 003 GB Grid Connection Queue Wednesday Edition

What moved in the GB grid connection queue this week

From this issue, the Grid Queue Pulse publishes every Wednesday. 3 queue movements and 2 operational signals across monitored records. Every finding is verified before publication. Evidence packs are provided to subscribers.

5Signals detected
273 GWGate 1 + Gate 2 register capacityGeneration and storage projects classified Gate 1 or Gate 2 in the TEC register; excludes transmission-connected demand and blank-gate entries. Gate 1 does not reserve capacity or a queue place.
GBTransmission + distribution
Connection Queue 12 July 2026
Newarthill Energy Park · 300 MW
Newarthill Energy Park 275kV Substation
This project entered the transmission connection queue at Gate 2 — a direct gated entry, confirming a connection offer has been formally made. The prior NESO TEC register recorded this project as not gated; no Gate 1 stage was observed in monitored records.
Verified · evidence pack on file Request evidence →
Connection Queue 12 July 2026
Kilgallioch Wind Farm · 274 MW
Kilgallioch 275kV Substation
This operating wind farm is recorded as not gated in the current TEC register. Cairnel’s comparison evidence shows a register churn event around the same time; the current not-gated status is confirmed from the latest edition.
Verified · evidence pack on file Request evidence →
Connection Queue 12 July 2026
Noventum Yaxley · 150 MW
North Anglia Connection Node E 400kV Substation
This project was newly classified Gate 1 in the transmission connection register. Gate 1 keeps a project in the connections process but does not reserve capacity or a queue place.
Verified · evidence pack on file Request evidence →

Monitor the projects that matter to you

The Pulse is the market picture. Your subscription is your deal picture — named projects, weekly status confirmation whether or not anything changes, and an alert the day it does.

Here’s what Cairnel currently knows about one of the largest projects in the queue: Kilmarnock BESS fact sheet →

Submit three projects for a coverage check →

Monitor tier from £300/month · payment link sent after coverage review · View plans

Coverage reflects records Cairnel had matched as at 15 July 2026.

Public-data acknowledgements

Cairnel uses multiple sources to build the picture. Some of the public ones that need referencing are National Energy SO and Elexon.

  • Supported by National Energy SO Open Data. Licence.
  • Contains BMRS data © Elexon Limited copyright and database right 2026. Licence.

Cairnel launched in July 2026. This is Issue 003. The Pulse is produced weekly — every item is verified before it appears here. We are early and we know it. If something looks wrong, or you want to suggest a project we should be watching, write to us: hello@cairnel.co.uk